Analysis · MENA · 22 May 2026

MENA is moving wind procurement from megawatts to round-the-clock firm output

Oman has signed a 2.7 GW round-the-clock hybrid and plans a 1,000 MW round-the-clock tender, and these contracts pay wind for the hours solar leaves empty.

Photo: Oleg Seliverstov, CC BY 3.0, via Wikimedia Commons

MENA is starting to buy wind by the hour as well as by the megawatt.

Three recent moves point the same way. Oman’s Nama Power and Water Procurement has awarded O-Green Energy a 2.7 GW wind, solar and storage contract, the first of two planned round-the-clock plants, and plans to tender a 1,000 MW round-the-clock project at a capacity factor above 70 percent this year. Saudi Arabia is tendering battery storage in tranches, 3 GW and 12 GWh in the second alone, which we read as the firming layer its wind fleet will need. In the UAE, Masdar and EWEC are developing a gigascale solar and battery project designed to deliver 1 GW of baseload around the clock. The common thread is procurement that pays for firm output.

My read is that wind is what holds the hybrid contracts together. A round-the-clock plant has to deliver after sunset and through the evening demand peak, which is exactly when solar output falls away. A solar-only firm contract crosses those hours on batteries alone. A wind-paired contract does not.

In our reading, that re-prices what a wind project is worth. Under a standard power purchase agreement, a developer is paid for energy whenever the wind happens to blow. Under a round-the-clock contract, wind is paid for filling the hours solar leaves empty, and a strong night or summer wind profile becomes a commercial asset.

If 2025 was the year MENA proved wind could be cheap, will 2026 be the year it proves wind can be firm?