Analysis · Oman · 26 August 2026

Oman tenders a renewables study for Musandam, where peak demand is forecast at 130 MW by 2031

Nama PWP put the Musandam study on sale on 24 August, covering solar, wind, hybrids and storage, with bids closing on 24 September.

Photo: Tom Brewster Photography, CC BY 2.0, via Wikimedia Commons

Musandam is home to about 54,000 people, an Omani enclave bordered by the UAE. Its power system has the same isolation. The Oman Observer reported in 2023 that the governorate is served by local standalone systems unconnected to the national grid.

On 24 August, Nama Power and Water Procurement (Nama PWP), the country’s sole power buyer, put a tender on sale for the Musandam Renewable Energy Feasibility Study. A techno-economic consultant will assess solar PV, wind, hybrid configurations and battery storage, then judge which of them is technically and economically justified there. Documents are available until 3 September. Bids close on 24 September at noon Oman time.

Here is the number that makes this worth watching. Nama PWP’s seven-year statement, published in March, forecasts Musandam peak demand growing from 91 MW in 2024 to 130 MW in 2031. Average demand moves from 52 MW to 73 MW. About 5% a year, on a system whose peak will be around 130 MW five years from now.

Set that against what this region now tenders. My read is that Musandam’s entire projected 2031 peak is the size of one mid-sized wind farm.

That gap is the point. In my view MENA built its wind procurement for gigawatts, with twenty-year offtake and development-bank debt stacks. Musandam poses a smaller and harder question. Does the same technology, and more importantly the same contract structure, work at a fraction of that size?

Nama PWP has weighed two routes here. One is connecting Musandam to the neighbouring UAE network. The other is building generation locally. The tender closing on 24 September pays someone to price the second route properly.

So my question for anyone developing wind in the Gulf. If the study comes back saying wind works in Musandam, is there a developer in this market built to deliver at that size, and a contract structure to put it under?